Production (Scheduled Operations)
Production (Scheduled Operations)
Production (Scheduled Operations)
Besides other tabs under Operations of plan specifications, there is also Production tab available enabling you to view scheduled lines of material in work orders.

Specifying Fields:
Priority |
Displays resource priority. Priorities can be set in Resource priority code list (double click in Priority field or go to Settings\Manufacturing\Resources\ Resource priority). |
Resource |
Select an ID of resource where operations is executed.
Optional field: In order to calculate production costs select number of resources when executing an operation.
Operation can be executed on multiple resources.
|
Start |
Enter or select start date of operation that can be found among scheduled data when issuing work order and can be changed if required. |
End |
Enter or select end date of operation that can be found among scheduled data when issuing work order and can be changed if required. |
Ouota (Norm) |
Enter production time normally required for operation that can be found among scheduled data when issuing work order and can be changed if required. |
U/M |
Displays the main unit of measurement according to the time constant. |
Line Finished |
If checked, displays whether line was issued (completely) or not. It is closed automatically when production time which was required is the same as planned when issuing work order. |