Pri kreiranju delovnih nalogov želim, da se upoštevajo tudi pripravljalno zaključni čas (Tpz). Kako lahko to storim?
|
|
|
|
Rank: Newbie
You have been a member since:: 24/09/2013(UTC) Posts: 0
|
To nastavitev aktiviram na Administratorski konzoli -> Proizvodnja -> Delovni nalogi -> Kreiranje DN -> Upoštevanje parametrov za pripravo dela. Preklopnik omogoča upoštevanje pripravljalno zaključnih časov (Tpz) pri kreiranju DN: iz plana oz. iz obdelave DN-
V kolikor je preklopnik izključen, se časi Tpz ob kreiranju DN ne prenesejo na proizvodno kosovnico iz terminskega plana.
|
|
|
|
Forum Jump
You cannot post new topics in this forum.
You cannot reply to topics in this forum.
You cannot delete your posts in this forum.
You cannot edit your posts in this forum.
You cannot create polls in this forum.
You cannot vote in polls in this forum.
Orange-Grey Theme Created by Ingo Herbote (WatchersNET.de)Powered by YAF 1.9.6.1 Under DNN |
YAF © 2003-2025, Yet Another Forum.NETThis page was generated in 0,462 seconds.