PANTHEON™ Help

 Toc
 PANTHEON Help - Welcome
[Collapse]PANTHEON
 [Collapse]Guides for PANTHEON
  [Expand]Guide for PANTHEON
  [Expand]Guide for PANTHEON Retail
  [Expand]Guide for PANTHEON Vet
  [Expand]Guide for PANTHEON Farming
 [Collapse]User Manuals for PANTHEON
  [Expand]User Manual for PANTHEON
  [Expand]User Manual for PANTHEON Retail
  [Expand]User manual for PANTHEON Vet
  [Expand]User Manual for PANTHEON Farming
[Collapse]PANTHEON Web
 [Collapse]Guides for PANTHEON Web
  [Expand]Guide for PANTHEON Web Light
  [Expand]Guide for PANTHEON Web Terminal
  [Expand]Guide for PANTHEON Web Legal
  [Expand]Old products Archive
 [Collapse]User Manuals for PANTHEON Web
  [Expand]Getting started PANTHEON Web
  [Expand]User Manual for PANTHEON Web Light
  [Expand]User Manual for PANTHEON Web Terminal
  [Expand]User Manual for PANTHEON Web Legal
  [Expand]Old products Archive
[Collapse]PANTHEON Granules
 [Collapse]Guides for PANTHEON Granules
  [Expand]Personnel Granule
  [Expand]Travel Orders Granule
  [Expand]Documents and Tasks Granule
  [Expand]Dashboard Granule
  [Expand]B2B Orders Granule
  [Expand]Field Service Granule
  [Expand]Fixed Assets Inventory Granule
  [Expand]Warehouse Inventory Granule
 [Collapse]User Manuals for PANTHEON Granules
  [Expand]Getting started
  [Expand]Personnel Granule
  [Expand]Travel Orders Granule
  [Expand]Documents and Tasks Granule
  [Expand]B2B Orders Granule
  [Expand]Dashboard Granule
  [Expand]Field Service Granule
  [Expand]Fixed Assets Inventory Granule
  [Expand]Warehouse Inventory Granule
  [Expand]Archive
[Expand]User Site

Load Time: 484.3818 ms
"
  6613 | 1 | |
Label


Completed work – MF

The form Completed work is used for reporting work done in a work operation line.

The form displays the work order (WO) and the selected line of the work operation together with the planned or remaining time of the operation. It contains fields for reporting the work completed and the quantities of good and bad pieces as well as pieces for repair produced. You can also check the data of the previously reported work for the selected line.

Operation time can be recorded using the function Start-Stop for automatically recording the time spent or by entering the quantities manually.

After entering the data, the reported data is confirmed. Upon confirmation, the corresponding documents for issuing work operation, receiving the product and issuing scrap are created and are immediately visible in PANTHEON.

HINT

For more information on how to use the form, see the chapter Completed work – MF in the user manual.

 

If you are using a tablet or a mobile device data in the footer and work history sections by clicking the  (Three dots) button at the bottom of the form.

Buttons for work recording are also displayed at the bottom of the form. You can read more about their functionalities in the footer section of this chapter.

 

To open the form, select Manufacturing | Work orders from the menu and click one of the WO cards. Then click the tab Operations. From the list, select the work operation card for which you want to report the quantities issued.

Below is a description of the form's features:

Contents

  1. Toolbar
  2. Header
  3. Reported data
  4. Footer
  5. Work history

 

1. Toolbar

The toolbar of the form Completed Work shows the form name and the following buttons:

Work orders

Clicking the tab opens the Work orders form.

Materials

Clicking this tab opens the form Materials for the selected WO. The form shows details of the material requirements for the WO.

Operations

Clicking the tab opens the Operations form for the selected WO. The form shows details of the work operations for the WO.

Completed work

The currently open tab.

X (Close)

Closes the form Completed Work and returns to the form Operations.

 

2. Header

In the header of the form, you can record the work using automatic time recording function Start-Stop. It also shows the details of the WO operation.

Key The key of the WO where the released operation is located.

Resource

Shows the ID of the resource used for the selected work operation.

Line The number of the line where the selected work operation is located on the finished product BOM.

Operation

The operation item ID.

Confirm receiving

If the toggle button Confirm receiving is enabled, the received quantities are confirmed upon clicking the toolbar button Confirmation. The documents for issuing work operation and receiving the quantities for the corresponding warehouses are created.

The documents are immediately visible in PANTHEON.

Finish Task

If the toggle button Finish task is enabled, the status of the operation changes to Finished upon clicking the toolbar button Confirmation.

The WO status changes automatically when the planned quantity is reached.

3. Reported data

The fields are used to enter the start of the operation and the time used. Enter the quantities received (good pieces, repairs, scrap pieces) and enter any note.

Time used / Planned

When using automatic time recording function, the time recorded is automatically entered in the field. Time counter is displayed in the field along with the icon that shows the state of the time recording (ongoing, paused, stopped).

If automatic time recording is not used, enter the time used for the operation in the field.

The time planned for operation is also displayed here.

Date The date of operation completion, which can be changed by entering a new date or selecting a date from the displayed calendar.
Good Pcs Enter the quantity of good pieces. The quantity of planned and still missing mieces is also displayed.
Repair The quantity of pieces for repair.
Scrap Pcs The quantity of scrap pieces received.
Note

Enter any text as a note for the completed work line.

Image The image of the item (product of the operation), if it has been added to the Items register.

 

HINT

In some fields, you can enter quantities using the plus + and minus - buttons. Pressing the button increases or decreases the quantity by one (1) unit.


4. Footer

In the footer of the form Completed Work, you can find the quantities already reported, confirm receiving and complete the task.

Issued quantity / Planned

The quantity of good pieces already issued and the planned quantity and the unit of measurement of the item.

Displayed in the following format: 4/7 PCS, which means that four of seven planned pieces have been produced.

Time used / Planned

The reported and planned run time of the operation.

Displayed in the following format: 01:00/1.24 MHR, which means that 1:00 man-hour of 1.24 man-hours have been completed.

Employee The details of the currently logged-in user.
 Start 

Clicking the button Start starts the automatic time recording function. 

If time recording is active, entering quantities on the form is disabled.

 Pause work

Clicking the button Pause work pauses the automatic time recording function.

When automatic time recording is paused, entering quantities on the form is disabled.

 Continue

Clicking the button Continue continues time recording after a pause.

If time recording is active, entering quantities on the form is disabled.

 End

Clicking the button End stops the automatic time recording. The recorded time is entered in the field Time used / Planned.

 Cancel Clicking the button cancel the time recording. The time counter in the field Time used/Planned is reset.
Confirmation

Saves the entered data on the time spent and reported product quantities for each work operation on the WO.

Upon confirmation, linked documents for issuing work operations and receiving quantities to warehouse are created.

 

5. Work history

In the section Work history, the data on the work completed and the quantities received is recorded.

Employee Displays the employee who recorded the work completed.
Start  Displays the start time of the recording of the work completed.
Duration Displays the duration of the operation.
Pieces

Displays the pieces type and quantity of pieces produced with an icon:

 - Displays the qunatity of good pieces produced.

 - Displays teh quantity of pieces for repair.

 - Displays the quantity of scrap pieces received.

Note

The note entered when the work completed was recorded.

If the field contains a note, the balloon icon  icon is colored yellow. By clicking on the icon, you can read and further edit the note.

 

 

 

  

     