PANTHEON™ Help

 Toc
 PANTHEON Help - Welcome
[Collapse]PANTHEON
 [Collapse]Guides for PANTHEON
  [Expand]Guide for PANTHEON
  [Expand]Guide for PANTHEON Retail
  [Expand]Guide for PANTHEON Vet
  [Expand]Guide for PANTHEON Farming
 [Collapse]User Manuals for PANTHEON
  [Expand]User Manual for PANTHEON
  [Expand]User Manual for PANTHEON Retail
  [Expand]User manual for PANTHEON Vet
  [Expand]User Manual for PANTHEON Farming
[Collapse]PANTHEON Web
 [Collapse]Guides for PANTHEON Web
  [Expand]Guide for PANTHEON Web Light
  [Expand]Guide for PANTHEON Web Terminal
  [Expand]Guide for PANTHEON Web Legal
  [Expand]Old products Archive
 [Collapse]User Manuals for PANTHEON Web
  [Expand]Getting started PANTHEON Web
  [Expand]User Manual for PANTHEON Web Light
  [Collapse]User Manual for PANTHEON Web Terminal
   [Collapse]MF Work orders
    [Expand]Issued material - MF
    [Collapse]Work done - MF
      Reporting work done manually - MF
      Reporting work done using Start Stop function - MF
      Adding new operation - MF
    [Expand]Receive - MF
   [Expand]SE Work orders
  [Expand]User Manual for PANTHEON Web Legal
  [Expand]Old products Archive
[Collapse]PANTHEON Granules
 [Collapse]Guides for PANTHEON Granules
  [Expand]Personnel Granule
  [Expand]Travel Orders Granule
  [Expand]Documents and Tasks Granule
  [Expand]Dashboard Granule
  [Expand]B2B Orders Granule
  [Expand]Field Service Granule
  [Expand]Fixed Assets Inventory Granule
  [Expand]Warehouse Inventory Granule
 [Collapse]User Manuals for PANTHEON Granules
  [Expand]Getting started
  [Expand]Personnel Granule
  [Expand]Travel Orders Granule
  [Expand]Documents and Tasks Granule
  [Expand]B2B Orders Granule
  [Expand]Dashboard Granule
  [Expand]Field Service Granule
  [Expand]Fixed Assets Inventory Granule
  [Expand]Warehouse Inventory Granule
  [Expand]Archive
[Expand]User Site

Load Time: 390.6316 ms
"
  1000003450 | 222919 | 379389 | Updated
Label

Reporting work done manually – MF

The form Work done makes it easy to report the work completed for the selected WO operation. You can report time spent on operation, the quantity of good pieces and any shrinkage produced. Previously completed work for this work operation can also be viewed.

To search for a specific work order or several, we use filters.

HINT

For technical details on the forms Operations and Completed work, see the chapters Operations – MF and Work done – MF.

To learn more about reporting work using Start-Stop function, see chapter Reporting work done using Start Stop function - MF.

 

This chapter describes how to select a work operation on a WO, report time used and quantities of itmes produced and check the work completed for an operation.

CASE SUMMARY

The person responsible wants to start work on an operation. In PANTHEON Web Terminal, they open the form Work orders and enable the toggle button "Data from daily plan" to find the WOs that are scheduled for processing. They select WO 24-6000-000003 and operation #15 O-Cutting. When the job is finished, they report time used, the quantities produced and confirms the operation. This is done as follows:

  1. Opening the form MF Work orders
  2. Selecting the WO to be processed
  3. Selecting the desired operation
  4. Reporting time used
  5. Reporting the quantities produced
  6. Checking the work completed

 

1. Opening the form MF Work orders

In PANTHEON Web Terminal, the person responsible logs in and the form Work orders opens, with all the WOs created.

Next, they select the WO to be processed.

2. Selecting the WO to be processed

Filters are used to select one or more work orders.

To show the filters, they click on the Search button. There are several different filters available.

HINT

When filtering, it is important to note that the last selected filter is always saved. This avoids re-setting. If you want to reset the filters, there is a clear icon  which deletes all the search criteria entered in the filters at the same time.

In the toolbar of the form, the person responsible enables the toggle button Data from daily plan.

Only WOs that are scheduled for processing in the daily plan are displayed in the list.

From the list of WOs, they click the WO card with the WO number WO 24-6000-000003 and item line LARA3_FLOOR.

This opens the form Operations, where the cards of the planned work operations are displayed.

Then they can report the work completed for this work operation.

3. Selecting the desired operation

They click the work operation card Operation #15 O-Cutting.

This opens the form Work done.

Then, they use the automatic time recording function to track operation time.

4. Reporting time used

The person responsible reports time used on the operation by clicking on the Time used/Planned field and enters the amount of time using on-screen keyboard or using time input.

In our case they enter 03:45 with time input.

Then, they can report the quantities produced.

5. Reporting the quantities produced

In the field Good pcs, they enter the number of good pieces produced, in this case: 15.

As they produced all planned pieces, they continue to confirm receiving and finish task.

They click on the  (Additional settings) button and toggle the Confirm receiving and Finish task buttons.

They return by clicking the Back button and confirm the reported work by clicking the Confirmation button.

The program displays information that the record on the work completed has been successfully created. The window is closed by clicking the button OK.

They then check the work completed.

6. Checking the work completed

The person responsible clicks the Operations tab to return to the form Operations.

The graphically and numerically displayed data on the work operation card  #10 O-CUTTING indicates the progress in the completion of this operation.

Hint

For more detailed example of use for Work done - MF form, including use of Start-Stop function see chapter Reporting work done using Start Stop function - MF.

 

 

 

 

 


 