PANTHEON™ Help

 Toc
 PANTHEON Help - Welcome
[Collapse]PANTHEON
 [Collapse]Guides for PANTHEON
  [Collapse]Guide for PANTHEON
   [Expand]Settings
   [Expand]Orders
   [Expand]Goods
   [Collapse]Manufacturing
    [Collapse]Manufacturing Scheduling (MF)
     [Collapse]Daily Plan
       Calendar
      [Expand]Work orders/Employees
      [Expand]Closure
       Drag and Drop in Daily plan
       Posted Work
       Copy Daily Plan
      [Expand]Header
       Table View
      [Collapse]Daily Plan Report
        4L0 - Daily Plan
        4L1 - Material Requirements
        4L2 - Daily Plan Closure
      [Expand]Right mouse click functions
     [Expand]Plans
     [Expand]Work Orders
     [Expand]Issue Materials
     [Expand]Input Completed Work
      Enter Employee Work
     [Expand]Receiving of Products
     [Expand]Cost Analysis
     [Expand]Track Completed Work
     [Expand]Transfer Completed Work
     [Expand]Administration of Finished Work
     [Expand]Manufacturing Analysis
     [Expand]Finished Work Analysis
     [Expand]Work Order Reports
      Issue Overview
      Manufactured Products Overview (Serial Numbers)
     [Expand]Examples
    [Expand]Simple Manufacturing
    [Expand]MT Manufacturing
    [Expand]ZEUS production cube
   [Expand]POS
   [Expand]Service
   [Expand]Financials
   [Expand]Personnel
   [Expand]Analytics
   [Expand]Desktop
   [Expand]Help
   [Expand]Messages and Warnings
   [Expand]Additional programs
   [Expand]Old products
  [Expand]Guide for PANTHEON Retail
  [Expand]Guide for PANTHEON Vet
  [Expand]Guide for PANTHEON Farming
 [Collapse]User Manuals for PANTHEON
  [Expand]User Manual for PANTHEON
  [Expand]User Manual for PANTHEON Retail
  [Expand]User manual for PANTHEON Vet
  [Expand]User Manual for PANTHEON Farming
[Collapse]PANTHEON Web
 [Collapse]Guides for PANTHEON Web
  [Expand]Guide for PANTHEON Web Light
  [Expand]Guide for PANTHEON Web Terminal
  [Expand]Guide for PANTHEON Web Legal
  [Expand]Old products Archive
 [Collapse]User Manuals for PANTHEON Web
  [Expand]Getting started PANTHEON Web
  [Expand]User Manual for PANTHEON Web Light
  [Expand]User Manual for PANTHEON Web Terminal
  [Expand]User Manual for PANTHEON Web Legal
  [Expand]Old products Archive
[Collapse]PANTHEON Granules
 [Collapse]Guides for PANTHEON Granules
  [Expand]Personnel Granule
  [Expand]Travel Orders Granule
  [Expand]Documents and Tasks Granule
  [Expand]Dashboard Granule
  [Expand]B2B Orders Granule
  [Expand]Field Service Granule
  [Expand]Fixed Assets Inventory Granule
  [Expand]Warehouse Inventory Granule
 [Collapse]User Manuals for PANTHEON Granules
  [Expand]Getting started
  [Expand]Personnel Granule
  [Expand]Travel Orders Granule
  [Expand]Documents and Tasks Granule
  [Expand]B2B Orders Granule
  [Expand]Dashboard Granule
  [Expand]Field Service Granule
  [Expand]Fixed Assets Inventory Granule
  [Expand]Warehouse Inventory Granule
  [Expand]Archive
[Expand]User Site

Load Time: 390.6261 ms
"
  1000005024 | 224451 | 381934 | Published
Label

4L1 - Material Requirements

The 4L1 – Material Requirements report shows all the material needed for the opeartions on the daily task, according to the parameters from the Daily Plan Report form.

You can open the report by selecting 4L1–Material Requirements from the Daily Plan Report form, which can be opened by clicking the (Reports) button in the toolbox of the Daily Plan form.

Table of contents

  1. Information about the report
  2. Reported material requirements

Below is a description of the form's features.

1. Information about the report

This section contains the information about the report.

Daily plan

Displays the key of the daily plan on the report.

Date

Displays the date of the daily plan.

Shift

Displays the shift of the daily plan.

Superior

Displays the superior on the daily plan.

Company

Displays the company that the report was generated by.

User

Displays the user that generated the report.

Report generated

Displays the exact time when the report was generated.

Document Types

Displays the document types selected in the Document Types section of the Daily Plan Report form.

Date

Displays the time period for the report selected in the Parameters section of the Daily Plan Report form.

Visible only if the parameter field was not empty.

Daily Plan

Displays the daily plan key selected in the Parameters section of the Daily Plan Report form.

Visible only if the parameter field was not empty.

Employee

Displays the employee selected in the Parameters section of the Daily Plan Report form.

Visible only if the parameter field was not empty.

Resource

Displays the resource selected in the Parameters section of the Daily Plan Report form.

Visible only if the parameter field was not empty.

Work Order

Displays the work order selected in the Parameters section of the Daily Plan Report form.

Visible only if the parameter field was not empty.

Operation

Displays the operation selected in the Parameters section of the Daily Plan Report form.

Visible only if the parameter field was not empty.

Item type

Displays the resource selected in the Item types section of the Daily Plan Report form.

Department

Displays the department of the daily plan.

Status

Displays the status of the daily plan.

 

2. Reported material requirements

This section contains data about material requirements.

Material

Displays the ID of the material required, from the Items register.

Name

Displays the name of the material required, from the Items register.

U/M

Displays the unit of measurement of the material required, from the Items register.

Planned Qty

Displays the planned quantity of the material.

Planned Scrap

Displays the planned quantity of the scrap produced.

Planned waste

Displays the planned quantity of the waste produced.

Total

Displays the total quantity of the material needed.

 


 