PANTHEON™ Help

 Toc
 PANTHEON Help - Welcome
[Collapse]PANTHEON
 [Collapse]Guides for PANTHEON
  [Collapse]Guide for PANTHEON
   [Expand]Settings
   [Expand]Orders
   [Expand]Goods
   [Collapse]Manufacturing
    [Collapse]Manufacturing Scheduling (MF)
     [Expand]Daily Plan
     [Expand]Plans
     [Expand]Work Orders
     [Expand]Issue Materials
     [Expand]Input Completed Work
      Enter Employee Work
     [Expand]Receiving of Products
     [Expand]Cost Analysis
     [Expand]Track Completed Work
     [Expand]Transfer Completed Work
     [Expand]Administration of Finished Work
     [Expand]Manufacturing Analysis
     [Expand]Finished Work Analysis
     [Expand]Work Order Reports
      Issue Overview
      Manufactured Products Overview (Serial Numbers)
     [Expand]Examples
    [Expand]Simple Manufacturing
    [Expand]MT Manufacturing
    [Expand]ZEUS production cube
   [Expand]POS
   [Expand]Service
   [Expand]Financials
   [Expand]Personnel
   [Expand]Analytics
   [Expand]Desktop
   [Expand]Help
   [Expand]Messages and Warnings
   [Expand]Additional programs
   [Expand]Old products
  [Expand]Guide for PANTHEON Retail
  [Expand]Guide for PANTHEON Vet
  [Expand]Guide for PANTHEON Farming
 [Collapse]User Manuals for PANTHEON
  [Expand]User Manual for PANTHEON
  [Expand]User Manual for PANTHEON Retail
  [Expand]User manual for PANTHEON Vet
  [Expand]User Manual for PANTHEON Farming
[Collapse]PANTHEON Web
 [Collapse]Guides for PANTHEON Web
  [Expand]Guide for PANTHEON Web Light
  [Expand]Guide for PANTHEON Web Terminal
  [Expand]Guide for PANTHEON Web Legal
  [Expand]Old products Archive
 [Collapse]User Manuals for PANTHEON Web
  [Expand]Getting started PANTHEON Web
  [Expand]User Manual for PANTHEON Web Light
  [Expand]User Manual for PANTHEON Web Terminal
  [Expand]User Manual for PANTHEON Web Legal
  [Expand]Old products Archive
[Collapse]PANTHEON Granules
 [Collapse]Guides for PANTHEON Granules
  [Expand]Personnel Granule
  [Expand]Travel Orders Granule
  [Expand]Documents and Tasks Granule
  [Expand]Dashboard Granule
  [Expand]B2B Orders Granule
  [Expand]Field Service Granule
  [Expand]Fixed Assets Inventory Granule
  [Expand]Warehouse Inventory Granule
 [Collapse]User Manuals for PANTHEON Granules
  [Expand]Getting started
  [Expand]Personnel Granule
  [Expand]Travel Orders Granule
  [Expand]Documents and Tasks Granule
  [Expand]B2B Orders Granule
  [Expand]Dashboard Granule
  [Expand]Field Service Granule
  [Expand]Fixed Assets Inventory Granule
  [Expand]Warehouse Inventory Granule
  [Expand]Archive
[Expand]User Site

Load Time: 421.8795 ms
"
  1010 | 1295 | 336374 | Updated
Label

Input Completed Work

Input Completed Work

Input Completed Work

010383.gif

 

Selecting Input Completed Work in the Manufacturing menu opens a window where you can input data on work completed in work order operations. Entered data can be viewed in Browse work panel.

Here you can in a fast way enter multiple completed work operations in various work orders. Similar to the function for processing work operations in individual work orders when updating work orders in Manufacturing | Work Orders | WO Work Preparation.

Usually data related to work operations are being input as set in manufacturing specification (WO Work Preparation).

Having checked 51391.gifCreate WO Work Preparation you can enter also work operations that do not exist in manufacturing specification but are created using it at the same time when completed work will be input in the work order. Data are in this case displayed somewhat differently in the panel for issuing as displayed in the follow-up.

The procedure for issuing starts by selecting a report type - whether the checkbox for creating work order preparation is checked or not. Next thing to do is that you select a work order on which you want to report processing of work operations. This is followed by selecting a work operation to be used in report. Select an employee and input completed work. Continue with input of work completed by other employees for this work operation. Confirm finished work by clicking OK, thus creating an entry in work order. Select a new work order and repeat the procedure.

 

000001.gif If 51392.gifEnter Work for Employees Related to Operation is checked in Administration Panel (Administration Panel | Settings | Program Parameters | Manufacturing | Work Orders - Process WO | General tab), then you can enter work only for those employees related to operation.

The main section of Input Completed Work window offers the following fields:

 

Work Order Here you can select a number of work order where you want to record completed work. It represents a first step when entering.
Product Displays ID and name of a product being created in the work order.
(quantity) Displays a planned (released) quantity of products to be manufactured as well as the unit of measurement.
Released Displays the date on which a work order was released.
Order Displays number and line of sales order related to the work order.
Priority Displays work order priority
Create WO Work Preparation If checked, material lines in manufacturing spec will be created having entered the issue. Data in the bottom section are displayed somewhat differently as can be observed in the follow-up.

 

Below it you can see the following fields containing further information:

 

Alternate Displays alternate lines for work operation.
Line Displays a line number of work operation.
Priority Displays resource priority. Priorities can be set in Resource priority code list (double click in Priority field or go to Settings\Manufacturing\Resources\ Resource priority).
Resource Displays an ID of resource used in operation from manufacturing specification. 

Operation can be executed on multiple resources.

(Resource Name) Displays name of the selected resource.
Department Select a department linked to the line in work order which is recorded in line of document of movement. Which department can be set depends on settings of parameter Post to Department Set In which can be found in Settings | Program | Document Types | Work Orders. You can change department at will.

 

Posting by departments according to a set parameter:

  • Resource Register --> a line contains department of resource. If no department is entered with the resource, a work order department is entered.
  •  Work Order --> a line contains work order department.

Having checked Create WO Work Preparation, the department from work order is displayed in this field.

 
Cost Ctr. Display Cost center from work order. Cost center can be changed.
Operation Displays name ID and name of work operation.
Tsu Displays set up time for work operation.
Tpr Displays production time per unit of quantity in work operation.
Total Time Displays total manufacturing time (Tsu + Tpr) used to produce the quantity of products in work order.
Used Displays already entered time used for the work operation.
Remaining Displays the remaining time as difference between the regular and used time.
Used Displays time reported by this input.
 

 

Hold-Ups

Hold-Ups panel is shown if Holds-Ups option is selcted in Additional Filds for Entering Work. In this tab you can enter different reasons for Hold-ups that occured during execution of work for selected operation.

Hold-Up ID

Enter Id from Hold-Up register

Name Displays Hold-Up name
Time Enter duration of holdup

 

Scrap and Repairs

Scrap and repairs panel is shown if Scrap Reason option is selcted in Additional Filds for Entering Work. In this tab you can enter different reasons for Scrap that occured during execution of work for selected operation.

Scrap ID

Enter Id from Scrap Reasons register

Name Displays Scrap reason name
Scrap Qty Enter scrap quantity for selected scrap reason
 
Repair Qty Enter quantity for reapirs for selected scrap reason

Apart from Work Entry tab you can below observe the Browse Work tab. When you click it a panel opens containing a list of the entire completed work input. 

The structure of the displayed fields in which you can input completed work depends on the following parameters, that is, "Start - End of Operation, Time (h, min, sec), Good- Bad Pieces, Hold-Ups, Earnings Type, Type of Time, Recognized Time, Recognized Pcs, Tsu - Tpr" in Program Parameters. Not selecting them means they will not appear in the bottom section.

The bottom section offers three tabs where you can enter completed work:

 

Reg. No. Enter or select a registration number of employee, who carried out work on this operation.
Employee Select a name of employee (or group of employees) carrying out the work. You can select only among the actively-employed.
Date Select or enter a date of issue. The current date is set by default.
Start (1) Displays alternate entry of time using the hh:mm:ss format as defined with start/end, that is, using the dd:mm:yyyy hh:mm:ss format having checked Date Input at Start or End of Operations
End (1) Displays alternate entry of time using the hh:mm:ss format as defined with start/end, that is, using the dd:mm:yyyy hh:mm:ss format having checked Date Input at Start or End of Operations.
Time (2) Displays alternate entry of time used as expressed in decimal values.
Time (h) (3) Displays alternate entry of time used as expressed in round values.
Time (min) (3) Displays alternate entry of time used as expressed in minutes.
Time (sec) (3) Displays alternate entry of time used as expressed in seconds.
Good Displays the quantity of "good" operations in reported manufacturing time.
Bad Displays the quantity of "bad" operations in reported manufacturing time.
Hold-up Displays time of hold-up occurring when trying to execute an operation.
ET Displays types of earnings used in work order, that is, the default value as set in the Administration Panel under Settings | Program Parameters|Manufacturing|Work Orders.
Type of Time Displays ID for type of time.
  •  Tpr + Tsu
  •  Tpr
  •  Tsu
  •  Tpr+1xTsu  
Tpr Displays manufacturing time of operation that can be found in product specification.
Tsu Displays closing manufacturing time of operation that can be found in product specification.
Recogn. Pcs Displays a recognized quantity (comprised of "good" and bad" as mentioned above) in records of completed work.
Recogn. Time Displays recognized manufacturing time in records of completed work.
Price Displays value of the entered completed work.
Note Enter a text describing lines in track completed work. Enter it by clicking 25568.gif. When the item is updated the icon changes to 25570.gif.

The following two buttons are displayed in the bottom section:

 

OK Click it to confirm entered completed work in work operations.
Cancel Click it to cancel entered completed work - deletes displayed data.

 

You receive warnings when errors occur when entering data or when you have to confirm the requested operation in order to proceed.

 

Having the Exclusive WO Processing option switched on, work orders being processed are recorded. At the same time it enables you to process only one single work order. When a work order already was processed the following message is returned.
You are not allowed to make use of any other data input method (by creating new lines in panel WO Work Preparation - manufacturing specification). You have to confirm the entered data.
Before trying to input data on completed work for any other work operation, you have to confirm the entered data.
A warning returned informing you that you are unable to change work order unless you confirm the entered work order.
Canceling entered data by must be confirmed because all data are lost in this action.
If you try to close the issue window before confirming the entry, you have to confirm this because all data are lost in this action.

 

By checking 51408.gifCreate WO Work Preparation you can also enter work operations that do not exist in manufacturing specification. They are created at the same time when input of completed work is carried out. 

Lines created using the 51409.gifCreate WO Work Preparation option are assigned an Active status in report of work documentation.

The procedure used for entering and entry confirmation is the same as in issuing existing lines. The difference is in the way how work operations is defined:

 

Operation Select an operation ID displaying its name.
Resource Select a resource of operation. Whenever resource is changes data about the department is updated as well. That is, if Post to Department Set In is set to posting by Resource Register.
Used The already displayed time used for this operation.
Used Entered time used for this operation.

The procedure used for entering and entry confirmation is the same as in issuing existing material lines.

A check is run before actually trying to remove records. In case errors occur the following window appears:



 

Rate this topic